Public announcement of the environmental impact assessment information for the metal surface treatment and transformer production expansion project of Yunnan People's Electric Power Equipment Co., Ltd.
According to the relevant requirements of the 'Measures for Public Participation in Environmental Impact Assessment' (Order No. __ of the Ministry of Ecology and Environment),4the 'Environmental Impact Report for the Metal Surface Treatment and Transformer Production Expansion Project of Yunnan People's Electric Power Equipment Co., Ltd.' has been completed, and we are now soliciting opinions and suggestions from the public regarding environmental impacts.
1. Basic information about the project
Project Name: Metal Surface Treatment and Transformer Production Expansion Project of Yunnan People's Electric Power Equipment Co., Ltd.
Construction Location: Kunming New City High-tech Industrial BaseB-5-3Plot No.
Construction Scale: Project investment70ten thousand yuan, within the existing production plant of the enterprise, adding a metal surface treatment workshop and a transformer casting workshop. The area of the metal surface treatment workshop is approximately130square meters, and the transformer casting workshop is approximately3100square meters. The metal surface treatment uses a tin plating process, and the transformer uses resin casting. After completion, the metal surface treatment workshop will process metals120t/annually, with a transformer output of5000units/per year.
2. Contact information for the construction unit and environmental assessment unit
(1) Construction Unit
Construction Unit: Yunnan People's Electric Power Equipment Co., Ltd.
Address: Kunming New City High-tech Industrial BaseB-5-3Plot No.
Contact Person: Manager Fang
Contact Information:13888346091
Email:13888346091@139.com
(2) Environmental Assessment Unit
Preparation Unit: Yunnan Jiayan Environmental Engineering Co., Ltd.
Contact Person: Engineer Yang;
Contact Number:18788408452; Email:35675690@qq.com.
3. Environmental impacts and pollution prevention measures
Waste Gas: This environmental assessment proposes to add corresponding gas collection hoods, and after reasonably setting up fans, to treat waste gas generated during the transformer casting process through existing environmental protection facilities after collection to meet discharge standards.
Wastewater: During project operation, water usage is only for cleaning workpieces in the tin plating section, with very little water consumption. Since the cleaning wastewater contains tin plating solution, this environmental assessment considers this part of cleaning wastewater as hazardous waste, which will be collected and temporarily stored before being regularly entrusted to qualified units for disposal.
Noise: The noise from production equipment during project operation is relatively low. Through impact analysis, it can be seen that the project construction can meet the 'Environmental Noise Emission Standards for Industrial Enterprises at Factory Boundaries' (GB12348-2008) in terms of class standards.3.
Solid Waste: This expansion project will utilize existing general solid waste temporary storage rooms and hazardous waste temporary storage rooms. In the hazardous waste temporary storage room, new collection barrels for tin plating waste liquid will be added, with a volume of4, used to collect and temporarily store tin plating waste liquid. A collection temporary storage pool for cleaning wastewater will be set up with a volume of50L/, and corresponding anti-leakage measures will be taken. According to investigations, the existing general solid waste temporary storage room and hazardous waste temporary storage room can meet usage requirements.5m3.
4. Conclusion of Environmental Impact Assessment
The Metal Surface Treatment and Transformer Production Expansion Project of Yunnan People's Electric Power Equipment Co., Ltd. complies with national industrial policy requirements; the project is located in Kunming New City High-tech Industrial BaseB-5-3, which meets planning requirements and has a reasonable layout; the technology used in the project is advanced, and the environmental protection measures proposed in the environmental assessment and feasibility study are feasible, with pollutant emissions meeting standards, having minimal impact on the environment without changing existing environmental functions; there are no major risk sources in the project, and the risk prevention measures proposed in the environmental assessment are reliable and effective. Under careful implementation of environmental risk prevention and emergency measures, the project's environmental risk is at an acceptable level. From an environmental risk perspective, the project is feasible; through public announcements, public surveys, etc., it is known that local residents support this project; economic benefits have a positive effect; therefore, under strict implementation of environmental protection measures and risk prevention measures proposed in the environmental assessment, as well as strengthening supervision conditions, from an environmental protection perspective, project construction is feasible.""Three Simultaneities"", strengthening supervision conditions, from an environmental protection perspective, project construction is feasible.
.
(5) Scope of public opinion solicitation
(Surrounding units and individuals that may be affected by construction projects are welcome to express their opinions and suggestions on this project's environmental protection work.)
(6) Network connection for public opinion form
(The full text of Yunnan People's Electric Power Equipment Co., Ltd.'s Metal Surface Treatment and Transformer Production Expansion Project and public participation instructions are attached.)
(7) Ways and means for the public to submit opinions
Construction Unit: Yunnan People's Electric Power Equipment Co., Ltd.
(The public can download and fill out the public opinion form in the attachment and send it to the contact person's email address of the construction unit or submit it by mail or inform by phone.).. January fifteenth, twenty-fourth year.
(For downloading Yunnan People's Electric Power Equipment Co., Ltd.'s Metal Surface Treatment and Transformer Production Expansion Project announcement text please visit () link download.)
Related information

On May 31, the Kunming Small and Medium-sized Enterprises Digital Transformation Pilot Conference was grandly held at the Yunshang Digital Empowerment Industrial Park in Panlong District. The conference, themed 'Intelligent Start for the Future, Digital Leadership for Development', was jointly guided by the Kunming Municipal Bureau of Industry and Information Technology and the People's Government of Panlong District, Kunming. It was hosted by the Kunming Small and Medium-sized Enterprises Digital Transformation Promotion Center, Huawei Cloud Computing Technology Co., Ltd., and Kingdee Software (China) Co., Ltd.
View details2024/01/16